pmp mock exam - 3

Project Management Professional (PMP) - Online Sample Test for Certification exam Preparation


1. The primary benefits of meeting quality requirements are:


2. A category or rank given to products that have the same functional use but different technical characteristics is called the productís:


3. Project quality assurance:


4. A project manager is employed by a construction company and is responsible for the furnishing of the completed building. One of the first things that the project manager for this project should do is to write a:


5. A project manager purchases 3,500 widgets for his project. The widgets are delivered on time, but there are many defects in the paint that is on the surface of the widgets. The project manager returns the parts to the vendor for repair and rework. The vendor complains that the paint job quality was not specified in the contract and it is not his responsibility to repair the parts. It is likely that the parts will be repaired by the vendor because of:



6. A contractor is working on a fixed price contract that calls for a single, lump sum payment upon satisfactory completion of the contract. About halfway through the contract, the contractorís project manager informs the contract administrator that financial problems are making it difficult for the contractor to pay employees and subcontractors. The contractor asks for a partial payment for work accomplished. Which of the following actions by the buyer is most likely to cause problems for the project?


7. As the manager of the production department where electrical circuits are being made you observe the inspection station where the completed printed circuit assemblies are being inspected. In this operation the inspector takes the printed circuit assembly and puts it into a fixture. The fixture is part of a testing machine that has three digital readouts. The inspector records the readings on the three digital readouts on his inspection report. This is an example of:


8. A project manager discovers that there is a part of the project that contains some risk. His or her strategy with this risk is to subcontract the work to an outside supplier by using a firm fixed price contract. Which of the following is true?


9. The equivalent of cost reimbursable contracts is frequently termed:


10. A buyer extends a formal invitation that contains a scope of work that seeks a response that will describe the methodology and results that will be provided to the buyer. This is called:


Competitive Exams

1. PMP Practice Test - 2
2. PMP Practice Test - 1
3. PMP Mock Exam - 10
4. PMP Mock Exam - 9
5. PMP Mock Exam - 8
6. PMP Mock Exam - 7
7. PMP Mock Exam - 6
8. PMP Mock Exam - 5
9. PMP Mock Exam - 4
10. PMP Mock Exam - 3
11. PMP Mock Exam - 2
12. PMP Mock Exam - 1
13. PMP Sample Test - 10
14. PMP Sample Test - 9
15. PMP Sample Test - 8
16. PMP Sample Test - 7
17. PMP Sample Test - 6
18. PMP Sample Test - 5
19. PMP Sample Test - 4
20. PMP Sample Test - 3
21. PMP Sample Test - 2
22. PMP Sample Test - 1
23. PMP Mock Test - 10
24. PMP Mock Test - 9
25. PMP Mock Test - 8
26. PMP Mock Test - 7
27. PMP Mock Test - 6
28. PMP Mock Test - 5
29. PMP Mock Test - 4
30. PMP Mock Test - 3
General Science - Test - 01
  • A company called Symbol owns patent to what common item ? . Answer ..
  • Can't connect to local MySQL server through socket '/var/lib/mysql/mysql.sock' (2)
    English Phrases