pmp practice test - 7

Project Management Professional (PMP) - Online Sample Test for Certification exam Preparation


1. The Preliminary Scope Statement which is and output of the Develop Preliminary Project Scope Statement process, is an input to all of the following EXCEPT:


2. Which of the following statements are true regarding cost estimating techniques?


3. Schedule model data, which is an input of the schedule development process, includes all of the following EXCEPT:


4. You are the project manager for the software company that develops stock analysis software. You have been assigned to develop a new technical analysis tools to forecast the price of stock given its historical volatility based on Elliot Wave techniques. You need to gather necessary information to write the project scope management plan. Which of the following tools/ techniques will NOT be useful for you in this process?


5. You have been recently been assigned to provide an accurate project schedule for constructing a new 50-story casino, in Las Vegas, Nevada. You are evaluating the network diagram for the construction project, and are using the forward pass calculations to construct the schedule. You are trying to calculate the earliest start time for laying the foundation of the building. The expected duration for this task is 150 days. The task must be completed within 300 days, while the expected completion is within 220 days. The latest finish time is 200 days. Based on this information, what is the earliest start time of this task?



6. Which of the following process is involved with the completion and settlement of the contract?


7. Subject matter experts are resources that can provide very valuable information to the project. In which scope-statement processes are subject matter experts first utilized?


8. Contract documentation are an input to the contract closure process. Which of the following are NOT included as part of the contract documentation?


9. Which of the following statement are FALSE regarding the probability impact matrix technique?


10. Which of the following is NOT considered an organizational process asset?


Competitive Exams

1. PMP Practice Test - 8
2. PMP Practice Test - 7
3. PMP Practice Test - 6
4. PMP Practice Test - 5
5. PMP Practice Test - 4
6. PMP Practice Test - 3
7. PMP Practice Test - 2
8. PMP Practice Test - 1
9. PMP Mock Exam - 10
10. PMP Mock Exam - 9
11. PMP Mock Exam - 8
12. PMP Mock Exam - 7
13. PMP Mock Exam - 6
14. PMP Mock Exam - 5
15. PMP Mock Exam - 4
16. PMP Mock Exam - 3
17. PMP Mock Exam - 2
18. PMP Mock Exam - 1
19. PMP Sample Test - 10
20. PMP Sample Test - 9
21. PMP Sample Test - 8
22. PMP Sample Test - 7
23. PMP Sample Test - 6
24. PMP Sample Test - 5
25. PMP Sample Test - 4
26. PMP Sample Test - 3
27. PMP Sample Test - 2
28. PMP Sample Test - 1
29. PMP Mock Test - 10
30. PMP Mock Test - 9
  • What is taught at the Californian Academy of Tauromaquia ? . Answer ..
  • Can't connect to local MySQL server through socket '/var/lib/mysql/mysql.sock' (2)
    English Phrases
    Basic English Usage