1. A new project manager is about to begin creating the project’s scope of work. One stakeholder wants to add many items to the scope of work. Another stakeholder only wants to describe the functional requirements. The project is important for the project manager’s company but a seller will do the work. Which of the following would you advise the project manager to do?

 
 
 
 

2. After the kickoff meeting, two team members engage in a casual conversation about the project objectives and deliverables. It is clear they heard different messages during the meeting. One member is so adamant that the other member gives up arguing the point. After talking to the project manager, the second member confirms that the first member is mistaken. At this point, what is the BEST course of action?

 
 
 
 

3. During project execution, a project team delivers a project deliverable to the customer. However, the customer neither acknowledges the deliverable nor says if it is acceptable, although an approval is required. What is the BEST thing to do?

 
 
 
 

4. ______ recognizes that a project or phase should begin and commits the organization to do so:

 
 
 
 

5. A document that formally recognizes the existence of a project is a :

 
 
 
 

6. You are managing a six months project and have held bi-weekly meetings with your project sponsors. After five-and-a-half months of work, the project is on schedule and budget, but the sponsors are not satisfied with the deliverables. This situation will delay the project completion by one month. The MOST important process that could have prevented this situation is:

 
 
 
 

7. Reducing the impact of a risk event by reducing the possibility of its occurrence is:

 
 
 
 

8. Some organizations are now using 6 Sigma for quality control compared to the usual:

 
 
 
 

9. In which of the following project management process groups are the most time and money typically spent?

 
 
 
 

10. A supplier has withdrawn from your project. A new supplier has been retained. His labor forces are due to arrive at the job site tomorrow. You should :

 
 
 
 