1. The outputs from risk identification are usually contained in the document called a risk register. All of the following should be included in the risk register upon completion of the risk identification process EXCEPT:

 
 
 
 

2. Which of the following statements are true?

 
 
 
 

3. Product analysis is a / technique of which of the following prosses?

 
 
 
 

4. You are in the process of identifying and documenting the logical relationships among schedule activities. Which of the following are NOT outputs to this process?

 
 
 
 

5. You are using the three-point estimating technique to estimate the duration of a schedule activity. Which of the following is the correct formula for calculating variance assuming a beta distribution?

 
 
 
 

6. Your project team is already created the WBS, developed estimates for the work packages, and sequenced the project activities using the precedence diagramming method. Which action should be performed NEXT?

 
 
 
 

7. All of the following scheduling techniques account for resource limitations/ availability EXCEPT:

 
 
 
 

8. You are in the process of identifying and documenting the project roles and responsibilities and create staffing management plan. All of the following are environmental factors that should be considered during this process EXCEPT:

 
 
 
 

9. You are the project manger assigned to build the house. You have determined the dependencies between activities on the project. One of the activity dependencies is that the foundation of the house must be created prior to the construction of the frame which of the following is true?

 
 
 
 

10. You are the project manager at a utility company. Due to the recent rise in the cost of petroleum, your organization is exploring cheaper, alternative forms of energy. You have just completed the project Scope Planning process and created the Scope management plan. However, upon review, you have determined that the resulting project scope management plan is ambiguous and poorly written. A poorly written project scope management plan will directly impact all of the following EXCEPT:

 
 
 
 