1. The unique identifiers assigned to each item of a WBS are often known collectively as:

 
 
 
 

2. Performance reviews are held to:

 
 
 
 

3. Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components?

 
 
 
 

4. What are the best uses of PERT:

 
 
 
 

5. A complex project will fit best in what type of organization?

 
 
 
 

6. The review of key deliverables and project performance at the conclusion of a project phase is called:

 
 
 
 

7. Project scope is:

 
 
 
 

8. Which of the following could be an appropriate WBS code for a work package at the fourth level in a WBS where the top level code is 1.0?

 
 
 
 

9. Change requests can occur due to:

 
 
 
 

10. The sender of a message is responsible for:

 
 
 
 