Project Management Professional Competitive Exams.
User ID : Password : New User Registration
PMP Sample mock test
  • PMP Sample Test - 14
  • PMP Mock Exam - 21
  • PMP Sample Test - 15
  • PMP Mock Exam - 22
  • PMP Sample Test - 19
  • PMP Mock Test - 01
  • PMP Mock Test - 02
  • PMP Mock Test - 07
  • Risk Management - 01
  • PMP Sample Test - 11
  • PMP Sample Test - 18
  • PMP Tutorial
  • PMP Certification Exam
  • Project Management Offices
  • Budgeting
  • Leadership
  • Project characteristics
  • Initiating
  • Negotiation and Influencing
  • Project Risk Management
  • Monitoring and Controlling
  • Exam Pattern
  • Conflict Management
  • Why PMI Certification

    Project Management Professional - PMP Certification tutorials will help you to prepare and to test yourself for PMP Certification exams.

  • How to Prepare
  • Exam Pattern
  • Who can get Certified?
  • PMP - Steps involved
  • PMP TIPS
  • TIPS For Preparation
  • PMP Certification Exam
  • 1.4.3 What is a Project?
    Organizational Structures : Matrix Organizations

    Matrix Organizations

    Matrix organizations came about to minimize the differences between, and take advantage of, the strengths and weaknesses of functional and projectized organizations. The idea at play here is that the best of both organizational structures can he realized by combining them into one. The project objectives are fulfilled and good project management techniques are utilized while still maintaining a hierarchical structure in the organization.

    Employees in a matrix organization report to one functional manager and to at least one project manager. It's possible that employees could report to multiple project managers if they are working on multiple projects at one time. Functional managers pick up the administrative portion of the duties and assign employees to projects. They also monitor the work of their employees on the various projects. Project managers are responsible for executing the project and giving out work assignments based on project activities. Project managers and functional managers share the responsibility of performance reviews for the employee.
    Matrix organizations have unique characteristics. Let's have a look at how projects are conducted and managed and how project and functional managers share the work in this organizational structure.

    Project Focus in a Matrix Organization
    Matrix organizations allow project managers to focus on the project and project work just as in a projectized organization. The project team is free to focus on the project objectives without distractions from the functional department.
    Project managers should take care when working up activity and project estimates for the project in a matrix organization. The estimates should be given to the functional managers for input before publishing. The functional manager is the one in charge of assigning or freeing up resources to work on projects. If the project manager is counting on a retrain employee to work on the project at a certain time, the project manager should determine their availability up front with the functional manager. Project estimates might have to be modified if it's discovered that the employee they were counting on is not available when needed.

    Balance of Power in a Matrix Organization
    A lot of communication and negotiation takes place between the project manager and the functional manager. This calls for a balance of power between the two or one will dominate the other.
    In a strong matrix organization, the balance of power rests with the project manager. They have the ability to strong arm the functional managers into giving up their best resources for projects. Sometimes, more resources than necessary are assembled for the project, and then project managers negotiate these resources among themselves, cutting out the functional manager altogether.

    On the other end of the spectrum is the weak matrix. As you would suspect, the functional managers have all the power in this structure. Project managers are really project coordinators or expeditors with part-time responsibilities on projects in a weak matrix organization. Project managers have link to no authority, just as in the functional organization. On the other hand, the functional managers have a lot of authority and make all the work assignments. The project manager simply expedites the project.

    In between the weak matrix and the strong matrix is an organizational structure called the balanced matrix. The power is balanced between project managers and functional managers. Each manager has responsibility for their parts of the project or organization, and employees get assigned to projects based on the needs of the project, not the strength or weakness of the manager's position.

    Matrix organizations have subtle differences, and it's important to understand their differences. The easiest way to remember them is that the weak matrix has many of the same characteristics as the functional organization, while the strong matrix has many of the same characteristics as the projectized organization. The balanced matrix is exactly that a balance between weak and strong, where the project manager shares authority and responsibility with the functional manager.

    <<--
    -->>