Characteristics of the Process Groups
The progression through the project management process groups exhibit the same characteristics as progression through the project phases do. That is, costs are lowest during the Initiating processes and few team members are involved. Costs and staffing increase in the Executing process group and then decrease as you approach the Closing process group. The chances for success are lowest during Initiating and highest during Closing. The chances for risks occurring are higher during Initiating, Planning, and Executing, but the impacts of risks are greater during the later processes. Stakeholders have the greatest influence during the Initiating and Planning processes and less and less influence as you progress through Executing, Monitoring and Controlling, and Closing. |